Grind and Gravel Projects

Construction Notice

GRIND AND GRAVEL PROJECT UPDATE

 

TOWNSHIP(S): Three Oaks, Galien, Buchanan, Weesaw, Hagar, Benton


 
LOCATION(S) AND PROJECT ORDER: 

Order

GRIND

GRAVEL

Road

Termini

Township

1

Completed

4/24/23*

Lakeside Rd.

Forest Lawn Rd. to IN state line

Three Oaks

2

Completed

 

Hudson Lake Rd.

Olive Branch Rd. to IN State Line

Galien

3

Completed

 

Olive Branch Rd.

Nye Rd. to Beaver Dam Rd.

Galien

4

Completed

 

Beaver Dam Rd.

Buffalo Rd. to Olive Branch Rd.

Galien

5

Completed

 

Buffalo Rd.

Hamilton Rd to Beaver Dam Rd.

Galien

6

Completed

 

Second St. Rd.

Pardee Rd. to Village Limits

Galien

7

 4/26/23*

 

Warren Woods Rd.

Cleveland Ave. to Gardner Rd.

Weesaw

8

 4/27/23*

 

Wagner Rd.

Coveney Rd. to W. Clear Lake

Buchanan

9

 4/28/23*

 

Madron Lake Rd.

Wagner Rd. to Miller Rd.

Buchanan

11

 5/3/23*

 

Hicks Ave.

Roslin Rd. West to end

Benton

12

 5/3/23*

 

Hicks Ave.

Red Arrow Hwy. East to end

Benton

10

 5/2/23*

 

Kerlikowske Rd.

Coloma Rd. to twp line

Hagar


 
ESTIMATED DATES: Work and schedule is contractor and weather dependent*


 
PROJECT: A contractor started County grind and gravel projects on Monday, April 17, 2023. Additional projects and order will be updated on our website weekly. Road improvement construction will result in temporary road closures with a possible moving work zone. Motorists should anticipate possible temporary delays as work progresses. 


 
SAFETY BENEFITS: Grind and gravel projects will provide needed structure to road base which will be prime and double sealed later in the construction season. Improvement projects will correct some structural issues, provide greater stability and a smoother road surface. 

 

TRAFFIC RESTRICTIONS: Temporary road closures or traffic delays will occur when contractor and equipment is present. Traffic will be permitted through by the contractor when safe to do so. Please reduce speeds and be alert when traveling through work zones. Individuals might wish to seek alternative routes or be prepared for possible delays until work is completed.
 
 
QUESTIONS: For any questions regarding this process please contact the Road Department. Schedule and work is dependent on both contractor and weather. The website will be updated regarding anticipated road project order, which will be evaluated weekly for conditions. 


One Page PDF

Facebook Twitter Email

Other News in Road - Closures and Construction

Newsflash Construction Update

Sawyer Road Update

Posted on: May 24, 2023
Construction Notice

Paving Related Work Begins

Posted on: April 17, 2023