Countywide scratch and seal projects are underway by our contractor. Contractor will be working to prepare locations by prepping or milling butt joints for future paving operation. A contractor paver will be applying a corrective layer of asphalt on top of the existing road surface. Later this year the BCRD sealcoating team will then sealcoat over this area to provide protective structure to newly added asphalt. For further questions regarding this resurfacing technique please contact the Road Department office.
As information is updated, we will provide further anticipated dates. The contractor along with Road Department staff are working as efficiently as possible to complete these improvement activities. The contractor during joint milling (preparation) and paving operation will maintain one lane of traffic, traffic will be maintained by traffic control flaggers. The public should anticipate possible travel delays or seek alternative routes when crews are working. All dates are weather and contractor permitting.*
| Road Name | Termini | Township | Joint Preparation Work* | Paving Schedule* |
1 | Benton Center Road | Red Arrow Hwy. to Duncan Rd. | Benton | Joints Done | Pave 6/21 |
2 | - | - | - | - | - |
3 | Empire Avenue | Yore Ave. to Benton Center Rd. | Benton | Joints Done | Pave 6/21 |
4 | Deans Hill Road | Painter School Rd to Pucker St. | Berrien | Joints Done |
|
5 | Painter School Road | Deans Hill Rd. to M-62 | Berrien | Joints Done |
|
6 | Portage Road | US-12 to dirt | Bertrand | Joints 6/16 | Pave 6/25 |
7 | Galien-Buchanan Road | Boyle Lake Rd. to W. Clear Lake Rd. | Buchanan | Joints 6/16 |
|
8 | Able Road | Boyle Lake Rd. to 2000 ft. East of Boyle Lake Rd. | Buchanan | Joints 6/16 | Pave 6/25 |
9 | 4th Street | Madron Lake Rd. to City Limits | Buchanan | Joints 6/16 | Pave 6/25 |
10 | S. Wolcott Avenue | Sawyer Rd. to I-94 | Chikaming | Joints 6/17 |
|
11 | Hanover Road | Minnich Rd. to Township Line | Chikaming | Joints 6/18 |
|
12 | Minnich | W. Kaiser Rd. to Sawyer Rd. | Chikaming | Joints 6/19 |
|
13 | West St | Village/City Limits to End | Coloma | Joints Done | Pave 6/22 |
14 | Harrison Street | Hagar Shore Rd. to McCray St. | Hagar | Joints Done | Pave 6/22 |
15 | Tamarack Drive | Coloma Rd. to east/west ends | Hagar | Joints Done | Pave 6/22 |
16 | Baldwin Road | Browntown Rd. to Snow Rd. | Lake | Joints Done |
|
17 | Notre Dame Avenue | Marquette Woods Rd. to Grand Mere Rd. | Lincoln | Joints Done |
|
18 | - | - | - | - | - |
19 | North Lemon Creek Road | M-139 to US-31 | Oronoko | Joints Done | Pave 6/24 |
20 | Marquette Woods Rpad | Scottdale Rd. to M-139 | Royalton | Joints Done | Pave 6/24 |
21 | River Road | Pipestone Rd. to Naomi Rd. | Sodus | Joints Done | Pave 6/23&24 |
22 | Hillandale Road | Townline Ave. to Naomi Rd. | Sodus | Joints Done | Pave 6/23 |
23 | Three Oaks Road | Village Limits to Forest Lawn Rd. | Three Oaks | Joints Done |
|
24 | Bell Road | Third St. to Bond St. | Niles | Joints 6/19 |
|
25 | Ontario Road | Third St. to Adams Rd. | Niles | Joints 6/19 |
|
26 | Rosemary Road | Willow Dr. to end | Lake | Joints Done |
|
27 | Hathaway Place | Hinchman Rd. to End | Lake | Joints Done |
|
28 | Highland Avenue | Crystal Ave. to Euclid Ave. | Benton | Joints Done | Pave 6/21 |
29 | 17th Street | Fulkerson Rd. to Bell Rd. | Niles | Joints 6/19 |
|
30 | 13th Street | Stateline Rd. to Bell Rd. | Niles | Joints 6/19 |
|