GRIND AND GRAVEL PROJECT UPDATE #3

 

LOCATION(S) AND PROJECT ORDER: 

#

Road Name

Termini

(to)

Termini (from)

Township

Grind

Gravel

1

Brown Road

East Road

railroad

Chikaming

Completed

Completed

2

Wilson Road

Brown Road

end

Chikaming

Completed

Completed

3

Locke Road

Union Pier Rd

Red Arrow 

Chikaming

Completed

4/22/2021

4

Old M-60

Behner Road

city limits

New Buffalo

Completed

4/23/2021*

5

Freehling Rd

Hills Road

Coveney Rd

Oronoko

Completed

TBD*

6

Browntown

Cleveland Ave

Holden Rd

Baroda

4/26/2021*

4/27/2021*

7

Mill Road

Warren Woods

Hanover Rd

Weesaw

4/27/2021*

TBD*















*Dates are all subject to weather, contractor and project progression

 

START DATE: Wednesday, 4/14/2021

 

ESTIMATED END DATE: Contractor and weather dependent*


 
PROJECT UPDATE #3: Please see updated table regarding status of grind and gravel and anticipated order and timeline for projects. As additional projects are added, the website will be revised to reflect those changes. Road improvement construction will result in temporary road closures with a possible moving work zone. Motorists should anticipate possible temporary delays as work progresses. 


 
SAFETY BENEFITS: Grind and gravel projects will provide needed structure to road base which will be prime and double sealed later in the construction season. Improvement projects will correct some structural issues, provide greater stability and a smoother road surface. 


 
TRAFFIC RESTRICTIONS: Temporary road closures or traffic delays will occur when contractor and equipment is present. Traffic will be permitted through by the contractor when safe to do so. Please reduce speeds and be alert when traveling through work zones. Individuals might wish to seek alternative routes or be prepared for possible delays until work is completed.

 
QUESTIONS: For any questions regarding this process please contact the Road Department. Schedule and work is dependent on both contractor and weather. The website will be updated regarding anticipated road project order, which will be evaluated weekly for conditions. 


Link to one page printer friendly PDF

Facebook Twitter Email

Other News in Road - Closures and Construction