The remaining 2020 grind and gravel projects are currently under construction. The anticipated grinding schedule and order has been indicated in the table below. Gravel additions will begin the week of 9/28/2020 to the newly ground roads. The order and schedule is still being determined by Road Department staff and the contractor doing the work. If you have additional questions regarding these or any other county road project, please contact us by phone at 269-925-1196.
Road | Termini | Township | Anticipated Grind Date | Anticipated Gravel Date | Treatment |
Camp Madron Lake Rd. | Madron Lake Rd. to End | Buchanan
| -
| TBD | Gravel |
Tabor Rd. | Evans Rd. to Pipestone Rd. | Pipestone | - | TBD | Gravel |
Smith Rd. | Painter School Rd. to Pucker St. Rd. | Berrien | 9/21/20 | TBD | Grind & Gravel |
Fairland Rd. | M-139 to M-140 | Berrien | 9/22/20 | Start 10/5/2020* | Grind & Gravel |
Watson Rd. | City/Twp Line to Park Rd. | Pipestone | 9/23/20 | TBD | Grind & Gravel |
Snow Rd. | New Pavement (Near Cleveland Ave) to Spitzke Road) | Baroda | 9/25/20 | 9/29/020 - 10/1/2020* | Grind & Gravel |
Central Ave. | N. I-196 to Riverside Rd. | Hagar | 9/24/20 | TBD | Grind & Gravel |
*Dates are subject to change based on weather, contractor and progress. Dates will be provided to the best of our ability when known.